Phase I Update

Phase I Photos

Item   Status
1. General Conditions Done
2. Site works, asphalt driveway Done
3. Shell Material Steel, concrete, forms, blocks (No sales Tax) Done
4. Labor for shell Done
5. Labor for Block masons Done
6. Pre cast Concrete Joists and installation for roof Done
7. Concrete pump, concrete finisher, heavy equipment Done
8. Exterior impact windows & doors as per plans ( No sales Tax) Done
9. Debris Hauling & clean up Done
10. Plumbing drainage for slabs & roof in 8” pipes Done
11. Electrical underground, site, panels, FPL underground, poles Done

Phase II Update

Phase II Photos

Item   Status
1. Handicap Ramp Done
2. Framing & drywall Work In Progress
3. Insulation Work In Progress
4. Plumbing & fixtures Done
5. HVAC Work In Progress
6. Electrical Work In Progress
7. Electrical Fixtures Work In Progress
8. Roof System Done
9. Stucco Done
10. Fire Sprinklers Work In Progress
11. Fire Alarm Work In Progress
12. Acoustical Ceiling Work In Progress
13. Paint interior & exterior Work In Progress
14. Debris hauling & clean up Work In Progress

Phase III Update

Item   Status
1. Pre cast copula Phase 3
2. Pre fabricated copper domes Phase 3
3. Ornamental Pre Cast stone Phase 3
4. Glass Railing & Aluminum handrail Phase 3
5. Kool Deck & floor finishes Phase 3
6. Millworks & Interior doors Phase 3